Sprint capacity calculator

Enter the sprint's working days, each person's hours and days off, and a focus factor: the sprint capacity calculator gives the team's capacity in hours and, from your past velocity, in story points.

Team days off are holidays everyone has. Below, give each person their days off, and their own hours a day only if they differ from the team's (blank uses the team's).

NameHours a dayDays off

The points finished in the last few sprints, separated by commas or spaces.

238 focus hours: 47.5 person-days of 10 working days, 340 hours, at 70% focus. That is 94.4% of what the same team would have with no days off.

Focus hours
238
Hours available
340
Person-days
47.5
Points to plan
33

Average velocity 35 points over 3 sprints; scaled to this sprint's hours, about 33.1 points. Plan for 33.

Capacity per person
PersonHours a dayDays offDays in sprintHoursFocus hours% of capacity
Ana8010805623.5%
Ben8286444.818.8%
Chen8010805623.5%
Dana4010402811.8%
Eli80.59.57653.222.4%
Team2.547.5340238100%

In short: Sprint capacity, or team capacity for one sprint, is the hours a team has for sprint work: each person's working days in the sprint, minus holidays and their days off, times their hours a day, times a focus factor for the time that really goes to the sprint. The example team has 340 hours, 238 of them focus hours, and its average velocity of 35 points scales to a plan of 33 points.

How to use the sprint capacity calculator

  1. Set the sprint. Enter its working days (10 for a two-week sprint of weekdays), any team days off such as a public holiday, the team's usual hours a day and a focus factor.
  2. List the people who will do the sprint work, up to 30. Give each one their days off, in halves if you like (0.5 is a half day), and their own hours a day only if they work different hours, such as a part-time developer.
  3. Add past velocity if you plan in story points: the points the team finished in its last few sprints. The calculator averages them and scales the average to this sprint's capacity.
  4. Read the capacity. The table shows each person's days, hours and focus hours and their share of the team's capacity. Copy it as text for the sprint planning notes, as CSV for a spreadsheet, or share a link that opens the same team.

Everything updates as you type and nothing leaves your browser. It replaces a sprint capacity planning template in Excel: the arithmetic per person, the team total and the points forecast are done for you, and a person with impossible figures, such as more days off than the sprint has, is named rather than quietly counted.

The sprint capacity formula, with an example

Capacity per person is (working days - team days off - their days off) x hours a day x focus factor, and the team's capacity is the sum. The example is a two-week sprint of 10 working days for five people on 8-hour days, with Dana part time at 4 hours, Ben off for 2 days and Eli for half a day, at a 70% focus factor:

Capacity per person in the example
PersonHours a dayDays offDays in sprintHoursFocus hours% of capacity
Ana8010805623.5%
Ben8286444.818.8%
Chen8010805623.5%
Dana4010402811.8%
Eli80.59.57653.222.4%
Team2.547.5340238100%

Eli has 9.5 days x 8 hours = 76 hours, and 70% of that is 53.2 focus hours. Added up, the team has 47.5 person-days, 340 hours and 238 focus hours. With nobody off, the same five would have 360 hours, so this sprint runs at 94.4% of full capacity. If a holiday such as Thanksgiving Day falls in the sprint, enter 1 team day off and the team drops to 304 hours; the business days calculator and the working days by month pages count the weekdays and US federal holidays between two dates for you.

Microsoft's guide to setting sprint capacity in Azure Boards describes the same inputs: capacity per day for each team member, their days off and the team's days off, and it notes that most teams set capacity in hours. In its words, “Capacity takes into consideration the variation in work hours by team members, as well as holidays, vacation days, and nonworking days.” Jira, Azure Boards and a spreadsheet all come down to the same arithmetic.

From capacity to story points: sprint capacity vs velocity

Hours do not turn into story points directly, because a point is a relative size that each team calibrates for itself. What carries over is the proportion. The example team finished 32, 38 and 35 points in its last three sprints, an average of 35. This sprint it has 94.4% of its full hours, so the forecast is 35 x 340 / 360 = 33.1 points, and the calculator rounds down to 33 to plan with. The forecast assumes the past sprints were run at full strength; if they were short-handed too, the average already undercounts and you can plan a little higher.

The focus factor does not move that number. At 60% focus the example has 204 focus hours instead of 238, but the points forecast stays at 33.1, because the velocity was earned at whatever focus the team really had. Use focus hours when the team plans tasks in hours, and the points forecast when it plans in story points.

The Scrum Guide treats this as a forecast, not a promise. On Sprint Planning it says: “the more the Developers know about their past performance, their upcoming capacity, and their Definition of Done, the more confident they will be in their Sprint forecasts.” Past performance is the velocity you type in; upcoming capacity is what this calculator works out.

Sprint capacity planning in practice

Collect days off before the planning meeting, not during it, and count the meeting days themselves: a sprint review, a retrospective and the planning session take hours that the focus factor should cover. Keep the same people on the list sprint to sprint, even when someone is out, so the availability percentage compares like with like. To keep the planning meeting itself to its time box, run it with the meeting timer, and the work hours calculator adds up a timesheet if you want to measure your real focus factor.

In Excel or Google Sheets, with the sprint's working days in B1, team days off in B2 and the focus factor in B3 (as 70%), a person with their hours a day in C5 and days off in D5 has =(B$1-B$2-D5)*C5*B$3 focus hours; fill it down and add the column. The Copy as CSV button pastes the whole table, totals included, ready to sort. For a full worked sprint, with Thanksgiving inside it and a focus factor measured from the team's own hours, read how to calculate sprint capacity.

Esta calculadora también está en español: calculadora de capacidad del sprint.

Questions people ask

What is the sprint capacity formula?

For each person, capacity = (working days in the sprint - team days off - their own days off) x their hours a day x the focus factor. Add everyone up for the team. In the example, Ben is off 2 days of 10, so he has 8 x 8 = 64 hours, and 44.8 focus hours at 70%. The team has 238.

How do I calculate sprint capacity in story points?

Start from velocity, not hours: average the points the team finished in its last few sprints, then scale that by this sprint's available hours as a share of the hours the same team has with nobody off. Velocities of 32, 38 and 35 average 35; this sprint has 94.4% of full hours, so the forecast is about 33.1 points, and the calculator suggests planning 33. Points and hours are not converted one into the other, because a point is a relative size, not a fixed number of hours.

What is the difference between sprint capacity and velocity?

Capacity is the time the team has in the coming sprint, in hours or person-days, after holidays, time off and part-time hours. Velocity is how much work, usually in story points, the team actually finished in past sprints. Capacity changes sprint by sprint; velocity is a history. Planning uses both: velocity says how much a full sprint usually holds, and capacity says how full this one is.

What focus factor should I use?

The share of a working day that really goes to sprint work, after meetings, email, support and interruptions. There is no standard figure; the calculator starts at 70% only as a place to begin. The best number is your own: divide the hours the team logged on sprint work by the hours it was available, over a few sprints. The focus factor changes the hours, not the points forecast, because the points come from your velocity, which already reflects how focused the team was.

How do I count holidays, part-time people and half days?

Enter a holiday everyone has in Team days off; it comes off every person's days. Give a part-time person their own hours a day (4 for half time on an 8-hour team), and leave the box blank for anyone on the team's hours. Days off can be halves or quarters: 0.5 is a half day. Someone out for the whole sprint can stay on the list with all their days off and counts zero.

Is anything I type sent anywhere?

No. The calculator runs in your browser. Copy share link puts the team, the days and the velocity in the part of the address after the #, which browsers never send to a server, so only the people you give the link to see it.